Kollam Bypass

From Wikipedia, the free encyclopedia
Jump to: navigation, search
Kollam Bypass
കൊല്ലം ബൈപ്പാസ്
Map of Kollam Bypass
Route information
Maintained by NHAI
Length: 8.16543884 mi (13.14100000 km)
Status: Under Construction
History: Planned in 1972
Major junctions
South end: NH66-IN.svg NH-66 in Mevaram
  Kollam-Kulathupuzha road in Ayathil
NH744-IN.svg NH-744 in Kallumthazham
NH183-IN.svg NH-183 in Kadavur
Kureepuzha road in Aravila
North end: NH66-IN.svg NH-66 in Kavanad
Location
Major cities: Downtown Kollam
Highway system

Kollam Bypass (Malayalam: കൊല്ലം ബൈപ്പാസ്) is a bypass road under construction in the NH 66 that bypasses CBD of the historic Kollam city in Kerala, India.The 13.141 km long bypass starts at Kavanad in the north to Mevaram in the south, via Aravila, Kadavur, Kallumthazham and Ayathil.[1]

History[edit]

Government of Kerala has proposed Kollam bypass project in 1972. The then Public Works Department minister Mr. T. K. Divakaran was the man behind Kollam bypass project. A stretch of 3 km from Mevaram to Ayathil has been completed in 1993 and 1.5 km Ayathil-Kallumthazham stretch has been completed in 1999. Kallumthazham-Kavanad stretch is still remaining.[2] This stretch includes three bridges, five culverts, one vehicle underpass, and five major intersections and needs to pass over the Ashtamudi Lake, the section will includes a seven- metre two-lane carriageway, paved shoulders and earthen shoulders.[3][4] The importance of the Kollam bypass is, it will touch 3 major National Highways(NH 66(Formerly known as NH 47), NH 183 (Formerly known as NH 220), NH 744 (Formerly known as NH 208)) passing through the state of Kerala.

Junctions[edit]

Latest developments on bypass project[edit]

  • 18 bidders have qualified for the bypass tender process - April 2014[5]
  • Government of India and Government of Kerala have decided to share the cost of Kollam bypass project equally - May 2014[6]
  • National Highway Authority of India is planning to re-tender the work with a change in estimate cost.[7][8]
  • Government of India has granted approval for Kollam bypass, a joint venture of the State and the Central governments in January 2015.[9][10]
  • Chief Minister of Kerala Oommen Chandy signed an agreement with a private company on 11 February 2015 to complete the works within 30 months. The total cost for works would be Rs.352 crore. The Government of Kerala has added the Kollam bypass project to its list of mega projects.[11]
  • Preliminary works for Kollam bypass has been commenced again on 4 March 2015 after a long gap. Currently, clearing of the way for bypass is going on here. Re-aligning of telephone cables, water pipelines and KSEB feeder lines will commence soon as part of this work.[12]
  • Mr. Nitin Gadkari, Union Minister for Road Transport and Highways and Kerala Chief Minister Mr. Oommen Chandy have jointly inaugurated the third phase construction work of Kollam bypass on 10 April 2015.[13][14]
  • 26 November 2017 is the final deadline for the completion of Kollam Bypass. If the construction company fails to meet the deadline, a fine will be imposed on the company based on the delayed days. Ram Dayal Sharma-Cherian Varkey Construction companies are jointly working on this project[15]
  • The construction work comes to a standstill due to the insufficiency of gravel. - October 2016[16]